It’s exciting times for our season ticket holders and customers at Bradley Park Golf Course as works to expand the existing Clubhouse begin.

Works will start on Monday 10th October 2016*, and are due to be completed by the first week in December.

The development will give you an extension to the clubhouse and the bar. In addition to this, a new decked terrace area which looks out over the golf course. There will be a moderate refurbishment to the toilets and changing areas and the addition of a disabled toilet.

In order to keep disruption to a minimum the work that is due to take place will happen in four phases. The initial plans involve the following work being carried out:

Phase One  10th October until 1st December* (8 weeks)
New extension to the back of the clubhouse -
• An exciting new decking area where you can sit and relax during warmer days and enjoy the view over the golf course
• Redecoration of the clubhouse
• New floor covering
• Construction of new extension, including bi-folding doors to decking

Phase Two  17th October until 1st December (7 weeks)
Work to the lobby area -
• Installation of disabled toilet with baby changing provision.

Phase Three  7th November until 28th November (3 weeks)
Work to the toilets and cloak room -
• Floor coverings
• redecoration
• New cubicles

Phase Four  14th November until 1st December (3 weeks)
Extension of the bar area -
• Redecoration including new floor covering
• New folding partitions
• New window blinds

We apologise in advance for any inconvenience the expansion to the Clubhouse may cause and thank you for your patience and understanding during this period.  If you have any queries regarding the new development please ask a member of staff or check back here.

*As with any development dates may change

Help & Guidance
Admissions Policy
Kirklees Active Leisure is a charitable trust limited by guarantee.
Registered Office: Stadium Business & Leisure Complex, Stadium Way, Huddersfield, HD1 6PG.
Charity No. 1091226, Company No. 4331165